Stormwater & Erosion Control (SWPPP)

When rain washes mud, concrete washout, fuel and trash off a construction site, it pollutes streams and storm drains. Most sites that disturb an acre or more need a stormwater permit and a Stormwater Pollution Prevention Plan (SWPPP). Everyone on site plays a part in following it.

Photo: silt fence along a site perimeter, a gravel construction entrance and a lined concrete washout area

Who needs a permit

Common controls

ControlPurpose
Silt fence, fiber rolls (wattles)Trap sediment before it leaves the site
Stabilized construction entrance (gravel pad)Knock mud off tires before trucks reach the street
Inlet protectionKeep sediment out of storm drains
Concrete washout areaContain high-pH washout water and solids
Seeding, mulch, erosion blanketsStabilize bare soil
Covered material and fuel storageKeep chemicals and debris out of runoff

Inspections

Permits require regular inspections, often every 7 days, or every 14 days plus within 24 hours after a significant storm, depending on the permit. Problems found must be fixed quickly and recorded.

What workers should do

Why it matters: violations can bring big fines and stop-work orders, and silica-laden slurry from saws counts as pollution too. See Walk-Behind Saws.

Standards & references